McDonald Elementary was constructed in 1927 and sits on 2.3 acres of land.
Under the 2026 transformational bond, the school would be completely renovated. Estimated renovation costs: $19,460,965. For an overview, see the one-page McDonald flyer.
Phase 1 (Years one to five)
- Secured vestibule/reception
- Restroom renovations
- Technology and furniture upgrades
Phase 2 (Years five to 10)
- Major renovations to classrooms, media center, gym, and hallways
- Adapt auditorium for cafeteria and kitchen upgrades
- Site improvements including parking, playgrounds, etc.
- Major mechanical replacement of steam pipe system
- New HVAC work including adding air conditioning
- Building enclosure including slate roof, windows, doors
- Major electrical replacement
- Major plumbing replacement
- Elevator replacement